Construction of River Capacity Enhancement Structure along Lagarian Creek, Quezon City (Phase VI)

CONSTRUCTION OF RIVER CAPACITY ENHANCEMENT STRUCTURE ALONG LAGARIAN CREEK, QUEZON CITY (PHASE VI) · 24OG0102

Contract amount₱49.5 million₱49,498,395.28 exactly · QC list p.3Contractor: JTC CRUZ CONSTRUCTION CO., INC.Completed
Budget
No data found
Released
No data found
Contract
₱49.5 million₱49,498,395.28 exactlyJTC CRUZ CONSTRUCTION CO., INC.Contract expiry: December 20, 2024QC list p.3
Built
Listed as “Completed”Completion date: no data foundQC list p.3
Audit
No data found

We found 2 of 5 records for this project. Missing: budget, released, audit. See sources