Peso LedgerFilipino

Construction of Flood Control Structure along Pasong Tamo Creek, Barangay Bahay Toro

CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG PASONG TAMO CREEK, BARANGAY BAHAY TORO, QUEZON CITY · 24OF0144

Contract amount₱19.1 million₱19,106,980.40 exactly · QC list p.1Contractor: OSCORD BUILDERS CORPORATIONOn-going
Budget
No data found
Released
No data found
Contract
₱19.1 million₱19,106,980.40 exactlyOSCORD BUILDERS CORPORATIONContract expiry: November 9, 2024QC list p.1
Built
Listed as “On-going”Completion date: no data foundQC list p.1
Audit
No data found

We found 2 of 5 records for this project. Missing: budget, released, audit. See sources