Peso LedgerFilipino

Construction of Flood Control Structure along Tullahan River and Tributaries, Barangay Sta. Monica

CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG TULLAHAN RIVER AND TRIBUTARIES, BARANGAY STA. MONICA, QUEZON CITY · 24OF0130

Contract amount₱95.5 million₱95,524,941.49 exactly · QC list p.3Contractor: LE BRON CONSTRUCTIONCompleted
Budget
No data found
Released
No data found
Contract
₱95.5 million₱95,524,941.49 exactlyLE BRON CONSTRUCTIONContract expiry: March 26, 2025QC list p.3
Built
Listed as “Completed”Completion date: no data foundQC list p.3
Audit
No data found

We found 2 of 5 records for this project. Missing: budget, released, audit. See sources