Construction of Flood Control Structure at Barangay San Bartolome, Quezon City (Phase Ii)

CONSTRUCTION OF FLOOD CONTROL STRUCTURE AT BARANGAY SAN BARTOLOME, QUEZON CITY (PHASE II) · 24OF0021

Contract amount₱48.5 million₱48,508,937.83 exactly · QC list p.3Contractor: AVE-MIRA CONSTRUCTION AND TRADINGCompleted
Budget
No data found
Released
No data found
Contract
₱48.5 million₱48,508,937.83 exactlyAVE-MIRA CONSTRUCTION AND TRADINGContract expiry: November 29, 2024QC list p.3
Built
Listed as “Completed”Completion date: no data foundQC list p.3
Audit
No data found

We found 2 of 5 records for this project. Missing: budget, released, audit. See sources