Construction of Flood Mitigation Structure at Barangay Payatas
CONSTRUCTION OF FLOOD MITIGATION STRUCTURE AT BARANGAY PAYATAS, QUEZON CITY · 24OF0018
Contract amount₱44 million₱44,002,896.50 exactly · QC list p.3Contractor: MRBII CONSTRUCTION CORPORATIONCompleted
- Budget
- No data found
- Released
- No data found
- Contract
- ₱44 million₱44,002,896.50 exactlyMRBII CONSTRUCTION CORPORATIONContract expiry: December 1, 2024QC list p.3
- Built
- Listed as “Completed”Completion date: no data foundQC list p.3
- Audit
- No data found
We found 2 of 5 records for this project. Missing: budget, released, audit. See sources