Rehabilitation of Flood Mitigation Structure along San Juan River, Quezon City (Phase Xv)
REHABILITATION OF FLOOD MITIGATION STRUCTURE ALONG SAN JUAN RIVER, QUEZON CITY (PHASE XV) · 23OG0038
Contract amount₱42.2 million₱42,208,516.89 exactly · QC list p.4Contractor: FRONT NINE KONSTRUCT (BUILDERS & REALTY DEVELOPMENT) CORPORATIONCompleted
- Budget
- No data found
- Released
- No data found
- Contract
- ₱42.2 million₱42,208,516.89 exactlyFRONT NINE KONSTRUCT (BUILDERS & REALTY DEVELOPMENT) CORPORATIONContract expiry: October 30, 2023QC list p.4
- Built
- Listed as “Completed”Completion date: no data foundQC list p.4
- Audit
- No data found
We found 2 of 5 records for this project. Missing: budget, released, audit. See sources