Rehabilitation of San Juan River (Phase Xiv)

REHABILITATION OF SAN JUAN RIVER (PHASE XIV), QUEZON CITY · 22OG0162

Contract amount₱21.8 million₱21,807,952.15 exactly · QC list p.4Contractor: AARCON BUILDERSCompleted
Budget
No data found
Released
No data found
Contract
₱21.8 million₱21,807,952.15 exactlyAARCON BUILDERSContract expiry: September 8, 2023QC list p.4
Built
Listed as “Completed”Completion date: no data foundQC list p.4
Audit
No data found

We found 2 of 5 records for this project. Missing: budget, released, audit. See sources