Construction of Flood Control Structure and Tributaries along Culiat Creek (Left Side) Barangay Bahay Toro
CONSTRUCTION OF FLOOD CONTROL STRUCTURE AND TRIBUTARIES ALONG CULIAT CREEK (LEFT SIDE) BARANGAY BAHAY TORO, QUEZON CITY · 22OF0022
Contract amount₱42.8 million₱42,777,000.00 exactly · QC list p.1Contractor: LARSEN-DUTCHER CONSTRACTOR CORPORATION (FORMERLY:LARSEN-DUTCHER CONSTRACTOR)Completed
- Budget
- No data found
- Released
- No data found
- Contract
- ₱42.8 million₱42,777,000.00 exactlyLARSEN-DUTCHER CONSTRACTOR CORPORATION (FORMERLY:LARSEN-DUTCHER CONSTRACTOR)Contract expiry: October 21, 2022QC list p.1
- Built
- Listed as “Completed”Completion date: no data foundQC list p.1
- Audit
- No data found
We found 2 of 5 records for this project. Missing: budget, released, audit. See sources