Construction of Flood Mitigation Structure along Marikina River, Phase 2, Barangay Bagumbayan
CONSTRUCTION OF FLOOD MITIGATION STRUCTURE ALONG MARIKINA RIVER, PHASE 2, BARANGAY BAGUMBAYAN, QUEZON CITY · 25OG0042
Halaga ng kontrata₱48.1 milyon₱48,131,264.15 eksakto · QC list p.1Kontratista: E.L. TORRES CONSTRUCTION AND TRADING INC. (FORMERLY : E. L. TORRES CONSTRUCTION & TRADINGOn-going
- Badyet
- Walang datos
- Nailabas
- Walang datos
- Kontrata
- ₱48.1 milyon₱48,131,264.15 eksaktoE.L. TORRES CONSTRUCTION AND TRADING INC. (FORMERLY : E. L. TORRES CONSTRUCTION & TRADINGTapos ng kontrata: Disyembre 18, 2025QC list p.1
- Naitayo
- Nakalista bilang “On-going”Petsa ng pagtatapos: walang datosQC list p.1
- Audit
- Walang datos
2 sa 5 rekord ang nakita namin para sa proyektong ito. Kulang: badyet, nailabas, audit. Tingnan ang mga pinagkunan